Answer:
a. Present value of $5,000 per year at 12% for 6 years*…………………………… $20,555
Present value of $12,000 at 12% at the end of 6 years**……………………… 6,084
Total present value of Project A…………………………………………………… $26,639
Less total cost of Project A………………………………………………………… 22,500
Net present value of Project A……………………………………………………… $ 4,139
* [$5,000 × 4.111 (Exhibit 2, 12%, 6 years)]
** [$12,000 × 0.507 (Exhibit 1, 12%, 6 years)]
b. Project A. Project A’s net present value of $4,139 is more than the net present
value of Project B, $3,500.